Verify that statutory tariff indexation and minimum volume protections do not force the project company into Year 1 lock-up.
Bankability memorandum attached to concession schedule
Where does debt service coverage break under volume, tariff and ramp delays?
01 · Live stress model
Steady-state gross concession revenue before downside shocks (USD 10m to 500m).
Split 45% fixed overhead and 55% variable operating expenditure (15% to 75%).
Total sculpted or annuity senior debt facility (USD 10m to 800m).
All-in fixed or hedged senior facility coupon (3.0% to 18.0%).
Level annuity repayment window inside the concession term (5 to 20 years).
Sustained demand or throughput deviation from base forecast (-50% to +25%).
Real tariff lag or unit fee compression (-40% to +25%).
Delayed commissioning quarters running at 40% baseline attainment (0 to 8 quarters).
Bars morph from the zero axis as inputs change. Dashed amber: 1.20x lock-up; dashed red: 1.05x default.
The model evaluates cashflow available for debt service (CFADS) against level annuity senior debt service across every year of the amortisation tenor. All equations are deterministic and reproducible by hand:
Limitations: assumes level annuity amortisation rather than custom sculpted principal, excludes corporate income tax holidays, value-added tax working-capital lags and reserve account drawdowns, and does not constitute a credit commitment.
02 · Year-by-year cashflow
| Year | Ramp | Stressed rev (USD m) | Opex + maint (USD m) | CFADS (USD m) | Debt service | Base DSCR | Stressed DSCR | Covenant |
|---|---|---|---|---|---|---|---|---|
| Year 1 | 70% | 33.91 | 19.52 | 14.39 | 24.51 | 1.44x | 0.59x | default |
| Year 2 | 100% | 48.45 | 22.72 | 25.73 | 24.51 | 1.44x | 1.05x | default |
| Year 3 | 100% | 48.45 | 22.72 | 25.73 | 24.51 | 1.44x | 1.05x | default |
| Year 4 | 100% | 48.45 | 22.72 | 25.73 | 24.51 | 1.44x | 1.05x | default |
| Year 5 | 100% | 48.45 | 22.72 | 25.73 | 24.51 | 1.44x | 1.05x | default |
| Year 6 | 100% | 48.45 | 22.72 | 25.73 | 24.51 | 1.44x | 1.05x | default |
| Year 7 | 100% | 48.45 | 22.72 | 25.73 | 24.51 | 1.44x | 1.05x | default |
| Year 8 | 100% | 48.45 | 22.72 | 25.73 | 24.51 | 1.44x | 1.05x | default |
| Year 9 | 100% | 48.45 | 22.72 | 25.73 | 24.51 | 1.44x | 1.05x | default |
| Year 10 | 100% | 48.45 | 22.72 | 25.73 | 24.51 | 1.44x | 1.05x | default |
| Year 11 | 100% | 48.45 | 22.72 | 25.73 | 24.51 | 1.44x | 1.05x | default |
| Year 12 | 100% | 48.45 | 22.72 | 25.73 | 24.51 | 1.44x | 1.05x | default |
03 · Comparative stress regimes
Full ramp from Quarter 1 with zero revenue shock clears the 1.35x sizing benchmark across every amortisation year.
| Regime | Minimum DSCR | Loan life cover (LLCR) | Engineering implication |
|---|---|---|---|
| Base case (0% shock) | 1.44x | 1.44x | Full ramp from Quarter 1 with zero revenue shock clears the 1.35x sizing benchmark across every amortisation year. |
| Lender downside (-15% vol, 2Q delay) | 0.59x | 0.99x | A two-quarter commissioning delay compresses Year 1 cover sharply even when steady-state cover remains above default. |
| Combined shock (-25% vol, 4Q delay) | 0.02x | 0.68x | Simultaneous volume and ramp shocks trigger 12 default breach years without debt sculpting or a funded six-month reserve account. |
Comparison of minimum DSCR and LLCR across base case, lender downside and combined severe shock regimes.
Source: Tie Wang deterministic DSCR stress model
04 · Why lenders test early
Credit committees never lend against an average ten-year coverage ratio. A concession that averages 1.45x over twelve years still defaults in Year 1 if two quarters of commissioning delay coincide with fixed operations-centre payroll and an ungraceful annuity schedule. Empirical World Bank data show that revenue-resilient infrastructure loans hold five-year default rates at Sourced pf-1 · 2023 Five-year cumulative default rate of revenue-resilient infrastructure loans (1995 to 2023), compared with 5.4% for non-revenue-resilient infrastructure debt World Bank, Infrastructure Monitor 2024 (published April 2025) Open public record ↗ , whereas unbuffered projects face far steeper loss rates during demand shocks.
Similarly, the European Investment Bank GEMs Consortium records an average annual public-counterparty default rate of Sourced pf-3 · 2024 Average annual default rate for public counterparties in multilateral development bank portfolios from 1994 to 2024 (90% confidence interval: 2.15% to 3.06%) European Investment Bank (GEMs Consortium), Default and recovery statistics: Public lending 1994-2024, October 2025 Open public record ↗ over three decades, with defaults jumping by Sourced pf-5 · 2020 Year-on-year jump in public-counterparty defaults in multilateral development bank portfolios in 2020 during the pandemic shock European Investment Bank (GEMs Consortium), Default and recovery statistics: Public lending 1994-2024, October 2025 Open public record ↗ during the acute 2020 contraction. Sizing senior debt against single-point forecasts ignores how quickly volume and tariff shocks compound when fixed operating costs cannot fall in line with revenue.
When this tester shows Year 1 default despite healthy steady-state coverage, the remedy is structural rather than cosmetic: pair a register-first software launch (so verified fees start before heavy hardware CAPEX) with an interest-only construction grace period, a funded six-month debt service reserve account, and explicit contractual tariff adjustment rules.
What remains outside this screening tool: foreign-exchange mismatch between local-currency tariffs and hard-currency debt, sculpted repayment tranches tied to seasonal commodity output, and step-in cure periods negotiated inside direct agreements with the public authority.
05 · Action by counterparty
Verify that statutory tariff indexation and minimum volume protections do not force the project company into Year 1 lock-up.
Bankability memorandum attached to concession schedule
Size senior debt principal and grace periods so stressed minimum DSCR holds above the 1.20x distribution lock-up line.
Downside sizing covenant table and DSRA requirement
Separate fixed overhead from variable field costs so operating margins cushion throughput dips without cutting SLA maintenance.
Fixed-versus-variable operating budget split
Complete pre-effective permits and site access before financial close to eliminate multi-quarter ramp delays.
Pre-effective readiness checklist removing ramp drag