Reserve land corridors for future passing-loop extensions and multi-user spur junctions before awarding an exclusive mineral concession.
Corridor right-of-way and open-access technical schedule
How many passing loops and trainsets are needed to move a target mineral tonnage?
01 · Live corridor model
Total single-track haul distance from mine loadout loop to port car dumper (50 to 1,200 km).
Full-consist crossing loops dividing the corridor into N + 1 ruling sections (2 to 30).
Contracted annual mineral export tonnage required from mine to port (2 to 60 Mtpa).
Standard heavy-haul consist length matching passing-loop clear length (40 to 250 wagons).
Net mineral load per gondola governed by axle-load limit (50 to 130 t).
Ruling-gradient average speed of loaded mineral trains (25 to 75 km/h).
Average speed of empty return consists from port to mine (35 to 90 km/h).
Mine flood-loading plus port rotary car-dumper unloading dwell per cycle (4 to 24 h).
Share of calendar hours available outside track maintenance possessions (65% to 95%).
Solid curve shows practical Mtpa capacity from 2 to 30 loops; dashed horizontal line marks target tonnage; dot marks active design.
Single-track bulk capacity is governed by the longest ruling block between adjacent passing loops, signalling clearance per meet and UIC 406 practical timetable recovery headroom:
Limitations: assumes uniform loop spacing and flat gradient symmetry; bankable corridor feasibility studies replace uniform blocks with dynamic train-performance simulation across actual elevation profiles and ruling bridges.
02 · Loop sensitivity table
| Passing loops | Avg section (km) | Ruling headway (min) | Practical capacity (Mtpa) | Margin vs target |
|---|---|---|---|---|
| 2 | 140.0 | 338.7 | 11.28 | -6.72 Mtpa |
| 4 | 84.0 | 208.0 | 18.36 | +0.36 Mtpa |
| 6 | 60.0 | 152.0 | 25.13 | +7.13 Mtpa |
| 8 | 46.7 | 120.9 | 31.60 | +13.60 Mtpa |
| 10 | 38.2 | 101.1 | 37.79 | +19.79 Mtpa |
| 14 | 28.0 | 77.3 | 49.39 | +31.39 Mtpa |
| 18 | 22.1 | 63.6 | 60.08 | +42.08 Mtpa |
| 24 | 16.8 | 51.2 | 74.61 | +56.61 Mtpa |
| 30 | 13.5 | 43.6 | 87.58 | +69.58 Mtpa |
03 · Phased corridor expansion
Minimal civil passing-loop footprint moves 12 Mtpa at low initial track CAPEX while preserving expansion sidings.
| Regime | Practical capacity | Fleet incl. spares | Engineering implication |
|---|---|---|---|
| Phase 1 corridor (12 Mtpa, 6 loops) | 20.9 Mtpa | 6 trainsets | Minimal civil passing-loop footprint moves 12 Mtpa at low initial track CAPEX while preserving expansion sidings. |
| Baseline mineral corridor (18 Mtpa) | 37.8 Mtpa | 7 trainsets | Ten evenly spaced loops hold practical timetable utilisation at 47.6%, comfortably below the 85% recovery ceiling. |
| Heavy-haul scale-up (38 Mtpa, 180 wag) | 90.1 Mtpa | 10 trainsets | Longer consists raise single-track throughput sharply without double-tracking, shifting the bottleneck to port tipplers. |
Comparison of practical capacity and rolling-stock fleet across Phase 1 starter, baseline and 38 Mtpa scale-up corridor configurations.
Source: Tie Wang heavy-haul capacity engine (deterministic browser model)
04 · Pit-to-port economics
World usable iron ore mine output stood at an estimated Sourced iron-1 · 2025 Estimated world usable iron ore mine production in 2025 (2,600,000 thousand metric tons) U.S. Geological Survey, Mineral Commodity Summaries 2026: Iron Ore Open public record ↗ in 2025, moved overwhelmingly over dedicated heavy-haul rail corridors to deep-water bulk terminals. Rail delivers a decisive environmental and safety edge over road trucking: International Union of Railways figures show rail accounts for just Sourced rail-2 · 2025 Share of total European Union transport external costs attributable to rail International Union of Railways (UIC), Global Rail Sustainability Report, 2025 Open public record ↗ of European transport external costs while freight rail emissions dropped Sourced rail-1 · 2025 Reduction in market-based freight rail CO2-equivalent emissions in the European Union since 2005 International Union of Railways (UIC), Global Rail Sustainability Report, 2025 Open public record ↗ since 2005.
Notice the diminishing returns in the loop curve once ruling headway approaches the 12-minute signalling clearance floor. Building 24 passing loops for a Phase 1 mine exporting 12 Mtpa traps hundreds of millions in idle ballast and turnouts. Tie Wang sizes initial civil formations for modular loop insertion while tuning mine loadout and port tippler cycle times to minimise locomotive capital.
05 · Action by counterparty
Reserve land corridors for future passing-loop extensions and multi-user spur junctions before awarding an exclusive mineral concession.
Corridor right-of-way and open-access technical schedule
Verify that practical single-track utilisation stays below 85% at bankable tonnage so minor derailments or weather outages recover cleanly.
Independent rail-capacity and rolling-stock sizing sign-off
Optimise mine loadout and port car-dumper dwell times before buying extra locomotives; cutting four hours of dwell can save entire trainsets.
Turnaround cycle and locomotive utilisation budget
Sequence passing-loop civil works in modular tranches matched to verified mine ramp-up rather than overbuilding Day-1 sidings.
Phased passing-loop civil expansion plan